| Test Venue | Task Name | Start | Finish |
| Floor 1 | NEES Hybrid Simulation Testing 2 DOF (Mosqueda/Ahmadizadeh) | Mon 7/10/06 | Mon 11/26/07 |
| 112 Ketter, AT Machine | MCEER/FHWA - Low Cycle Fatigue tests on Stainless Steel Rebar (Lee/Zhou) | Mon 7/30/07 | Wed 1/30/08 |
| Table 2 | MCEER Isolated Raised Floor System Test (Bruneau/Cui) | Mon 6/25/07 | Fri 3/14/08 |
| Floor 0 | FHWA - Hybrid FRP Fatigue Tests on Composite Bridge Deck (Aref/Warn) | Mon 10/8/07 | Fri 4/4/08 |
| Floor 1 (Laminar Box Base) | MCEER Collapse (Mosqueda/Tsitos) | Tue 11/13/07 | Thu 3/6/08 |
| Table 1 | SEESL Armstrong Suspended Ceiling Tests (Whittaker) | Mon 2/25/08 | Fri 2/29/08 |
| Table 2 | SEESL AREVA (Quebec) - Qualification Tests on Airswitches for Hydro Quebec (Confirmed) | Mon 3/10/08 | Thu 4/17/08 |
| NCS | NEESR-GC - Simulation of the Seismic Performance of Nonstructural Systems | Mon 3/3/08 | Fri 5/2/08 |
| Floor 0 | SEESL Laboratory Cleanup | Mon 5/5/08 | Fri 5/16/08 |
| Table 1 | SEESL Baltimore Aircoil Rooftop Unit (TENTATIVE) | Mon 5/19/08 | Mon 6/2/08 |
| Table 1 | NEESR-GC - Ports Phase 1 | Mon 7/14/08 | Tue 8/12/08 |
| Table 1 | SEESL Southern States Disconnect Switches (Tentative) | Mon 8/4/08 | Tue 9/9/08 |
| Table 1 | MCEER IEEE693 Qualification Electrical Substation Equipment (Reinhorn/Kong) | Fri 9/12/08 | Thu 10/16/08 |
| Laminar Box | NEESr NEESPiles FY08 | Tue 9/2/08 | Wed 6/10/09 |